Start from one enquiry reference
Give every item a reference that stays the same in your enquiry, supplier replies and purchase order. Attach the same drawing revision and requirement list to each request. If your requirement changes, send the revision to every supplier whose quotation you intend to compare.
Keep different sizes, materials and finishes on separate lines. A broad description such as “bolt set” leaves the supplier to decide what is included. Start with the fastener enquiry checklist when the original parts list still needs clarification.
Compare the same quantity and unit
Record whether the quoted unit is a piece, set, box or weight. Check the quantity of finished items that unit represents. Do not compare the price of one assembled set with the price of one loose component.
- Bolts with nuts and washers: list each component and the quantity included per set.
- Threaded rods: distinguish stock lengths from finished cut pieces; retain the required length and end-condition references.
- Boxed hardware: record the agreed pieces per pack and packs per carton.
If the counts differ or a weight-to-piece conversion is not documented, leave the price comparison unresolved and ask for a quotation on the same counting basis. The packing and order checklist helps keep that basis consistent through delivery.
Record differences before comparing totals
Place each supplier response beside the original requirement. Record an omitted detail as an open question. An omitted grade, finish, drawing revision or document is not confirmation that the supplier has included it.
Use a separate deviation note for every proposed change. Ask the supplier to identify the alternative by part reference and state what differs. Where project or engineering approval is required, obtain that review before treating the alternative as acceptable.
For a drawing-controlled bracket, check the bracket drawing handover checklist before deciding that two quotations describe the same part.
Blank quotation comparison table
Copy this table into a spreadsheet or print this page. The comparison cells are intentionally empty. Complete them from your own enquiry and supplier quotations; the table contains no example price or assumed product specification.
On small screens, scroll the table sideways to see all columns.
| Check | Your requirement | Quotation A | Quotation B | Open question |
|---|---|---|---|---|
| Item and drawing revision | ||||
| Exact dimensions and specification | ||||
| Quantity and counting unit | ||||
| Components included per set | ||||
| Required material and finish | ||||
| Required documents or inspection scope | ||||
| Packing and labels | ||||
| Unit price, currency and quotation validity | ||||
| Named delivery place and freight scope | ||||
| Additional or unconfirmed charges | ||||
| Samples and approval requirements | ||||
| Quoted timing and order conditions |
Separate the item price from the delivery scope
Record the quoted currency, price unit, quantity and validity date. Then compare packing charges, samples or inspection charges if applicable, the named delivery place, freight scope and the documents included. Keep any unconfirmed destination charge visible instead of treating it as zero.
Record requested and quoted timing separately, and ask what event starts the quoted lead time. Payment terms and other order conditions should be compared as written. This checklist does not set or promise BOLTPV prices, payment options, delivery dates or freight charges.
Close the questions in writing
Before issuing an order, identify which quotation revision you are accepting and resolve the remaining differences. Make sure the accepted specification, approved alternatives, packing and quantity basis appear in the final written agreement.
For an initial BOLTPV enquiry, send the part reference, specification, quantity, application and destination with your drawings or photos. You can use the existing blank hardware RFQ worksheet to prepare that original request.